Rapid KL LRT Hang Tuah-Masjid Jamek Through Trains Resumes from 1 February 2024

Rapid KL LRT Hang Tuah-Masjid Jamek Through Trains Resumes from 1 February 2024

LRT Ampang and Sri Petaling Lines Hang Tuah, Plaza Rakyat, and Masjid Jamek LRT Stations has resumed through train services from the main Ampang and Putra Heights branches from 1 February 2024.

This comes after the temporary repair work of the damaged viaduct structure and track near Bandaraya LRT Station has been completed, and trains are now running on the full line again, though without passengers on the previously-affected damaged viaduct structure and track near Bandaraya LRT Station during this testing phase.

LRT Bus Bridging Service LRT10 continues to cover the closed LRT sector between Masjid Jamek and Bandaraya.

The Bandaraya-Sentul Timur shuttle train continues to operate as a separate shuttle, though trains are already running on through services on the previously-affected damaged viaduct structure and track near Bandaraya LRT Station during this testing phase.

Rapid KL LRT Ampang and Sri Petaling Lines Disruption Route Map (Updated from 1 February 2024)

Rail Bridging Bus Service LRT10 • Masjid Jamek-Bandaraya

  • Masjid Jamek LRT Station
  • Bandaraya LRT Station

LRT Bus Bridging Service LRT10 will operate at a frequency of 10 minutes depending on traffic conditions.

Full Resumption of LRT Ampang and Sri Petaling Lines by 17 February 2024?

Rapid KL has announced that this testing phase will only be from 1 to 16 February 2024. It is possible that train services will be fully reinstated by 17 February 2024 if everything is good to go, since trains are already running without passengers on the previously-affected damaged viaduct structure and track near Bandaraya LRT Station during this testing phase.

Information is from the official Rapid KL press release here.